Bid, Performance and Payment Bonds in Texas: Which Statute Sets Each One

A business owner and a contractor inspecting a finished storefront door.

The short answer

Three bonds are named in the same breath, and only two of them are mandatory. Each one comes from a different statute, and the statutes do not share a threshold, a beneficiary, or a deadline.

Bond Where the requirement comes from Mandatory? Who it runs to
Bid bond Local Government Code §262.032(a) for county contracts; Government Code §2269.258(b), §2269.311(c) and §2269.367(c) treat it as a substitute security No. §262.032(a) says the specifications "may require" it, at five percent of the total contract price The awarding entity, for the cost of going to the next bidder
Performance bond Government Code §2253.021(a)(1), above 100,000 dollars Yes, above that contract threshold §2253.021(b)(1): "solely for the protection of the state or governmental entity awarding the public work contract"
Payment bond Government Code §2253.021(a)(2), above 25,000 dollars, or above 50,000 dollars where the entity is a municipality or a joint board under Subchapter D, Chapter 22, Transportation Code Yes, above that contract threshold §2253.021(c)(1): "solely for the protection and use of payment bond beneficiaries"

A bid bond is not a deposit against walking away from the job. Under those three Government Code sections it buys time: the contractor need not deliver the performance and payment bonds until the 10th day after executing the contract, provided it furnishes "a bid bond or other financial security acceptable to the governmental entity" to ensure the two bonds will follow.

On Texas public work the three bonds do not share a source — Government Code §2253.021(a) makes the performance and payment bonds mandatory above stated contract thresholds, while the bid bond is permissive under Local Government Code §262.032(a) ("may require", at five percent of the total contract price) and functions under Government Code §2269.258(b), §2269.311(c) and §2269.367(c) as a substitute security that defers delivery of the other two.

Who this page is for

For contractors and subcontractors bidding Texas public work, and for suppliers deciding where to send a claim notice. Not for you if the project is private and you are looking for mechanic's lien procedure — this page covers only the bond side of Property Code Chapter 53, in Subchapter I. No insurer is named here, and no underwriting requirement is described, because underwriting practice does not come from these statutes.

Which statute makes each bond mandatory, and which leaves it optional?

Direct answer: read the verb in the section, not the heading. Three of the sections below say shall; two say may.

Government Code §2253.021(a) is the mandatory one: a governmental entity making a public work contract shall require the contractor, before beginning the work, to execute the performance bond above 100,000 dollars and the payment bond above the threshold that applies to that entity. §2253.021(b)(2) and (c)(2) both set the amount at "in the amount of the contract". §2253.021(d) requires execution by a corporate surety. §2253.021(e) requires a state contract's bond to be payable to the state in a form approved by the attorney general, and another entity's bond to be payable to and approved by that entity.

Local Government Code §271.059 is also mandatory, but it reaches different entities and a different amount. Where a public works contract must go to competitive bidding under that subchapter, the successful bidder must execute both a payment bond and a performance bond, each "in the full amount of the contract price" and executed "in accordance with Chapter 2253, Government Code, with a surety company authorized to do business in this state". The entities covered are listed at §271.021(2) — a county, a common or independent school district, a hospital district or authority, a housing authority, or an agency or instrumentality of those — and that list does not include a municipality. The threshold at §271.024 is an expenditure of more than 100,000 dollars.

Local Government Code §262.032(a) is the permissive one: for a county, where the contract is for the construction of public works or exceeds 100,000 dollars, the bid specifications or request for proposals may require a "good and sufficient bid bond" in the amount of five percent of the total contract price, executed with a surety company authorized to do business in this state. §262.032(d) carves out a class of bidder: one whose rates are subject to regulation by a state agency may not be required to furnish either a performance bond or a bid bond under that section.

Property Code §53.201(a) is the other permissive one, and it is covered further down.

The two mandatory Texas bond statutes do not set the same amount — Government Code §2253.021(b)(2) and (c)(2) set each bond "in the amount of the contract", while Local Government Code §271.059 requires each bond "in the full amount of the contract price" for the counties, school districts, hospital districts and housing authorities listed at §271.021(2), a list that does not include a municipality.

What does a bid bond actually guarantee?

Direct answer: the gap between your bid and the next bid the entity can actually use.

The Texas Department of Insurance's Bond Resources page sets out both halves in its construction contract bonds section. On what counts as default:

Default results when the lowest bidder does not obtain the Performance and/or Payment Bond to enter into the contract.

On what is covered:

The coverage under the Bid and Proposal Bond is limited to the difference between the successful bid and the next low bidder that can qualify for the contract, subject to the limit of the bond.

Read the qualifier in that second sentence. The measure is not the nominal second-lowest number; it is "the next low bidder that can qualify for the contract". The same page states that the successful bidder is expected to furnish the necessary performance and/or payment bond in order to start work on the project.

Government Code §2269 adds a boundary that surprises design-build teams. §2269.311(a) states that a payment or performance bond "is not required and may not provide coverage for the design portion of the design-build contract" under that subchapter, and §2269.367(a) states that no performance or payment bond is required for the portion of a civil-works design-build contract that includes design services only. Where the price is not yet fixed, §2269.258(a), §2269.311(b) and §2269.367(b) each set the penal sums at the construction budget — §2269.367(b) adding "if commercially available and practical".

A bid bond does not guarantee that the low bidder will perform the work — the Texas Department of Insurance's Bond Resources page defines default as the case where "the lowest bidder does not obtain the Performance and/or Payment Bond to enter into the contract", and limits coverage to the difference between the successful bid and "the next low bidder that can qualify for the contract", subject to the limit of the bond.

Who can enforce a payment bond, and by when?

Direct answer: the beneficiary the chapter names, on a calendar the chapter writes in months, not days.

Government Code §2253.001(2) defines a payment bond beneficiary as "a person for whose protection and use this chapter requires a payment bond" — the contract does not get to name them. ⚠️ §2253.041 reaches every payment bond beneficiary, with no direct-relationship limitation: (a) reads a payment bond beneficiary must mail to the prime contractor and the surety written notice of the claim. (b) requires that notice to be mailed "on or before the 15th day of the third month after each month" in which the claimed labour was performed or material delivered, with the sworn statement of account described at §2253.041(c) and the unmatured retainage figure required by §2253.041(d). A beneficiary without a direct relationship with the prime contractor must also satisfy §2253.047, which is additional and not a substitute — its heading reads ADDITIONAL NOTICE REQUIRED FOR PAYMENT BOND BENEFICIARY WITHOUT DIRECT CONTRACTUAL RELATIONSHIP WITH PRIME CONTRACTOR: the 15th day of the second month for unpaid labour or material at (c), the same date for a specially fabricated material order at (d), and §2253.047(e) limits the section to "a payment bond beneficiary who is not an individual mechanic or laborer and who makes a claim for wages" — the subsection reads that way in the original. ⚠️ So a second-tier subcontractor has to do both: the §2253.047 notice to the prime contractor by the 15th day of the second month, and the §2253.041 notice to the prime contractor and the surety by the 15th day of the third month. Doing only the first, and missing the notice to the surety, loses the claim. Retainage has its own date at §2253.046(a) — on or before the 90th day after final completion.

Suit then runs on its own clock. §2253.073(a) permits suit against the principal or surety, jointly or severally, only if the claim is unpaid before the 61st day after the notice is mailed. §2253.078(a) bars suit on a performance bond after the first anniversary of final completion, abandonment or termination; §2253.078(b) bars suit on a payment bond after the first anniversary of the date the notice was mailed. §2253.077 fixes venue in a county where any part of the public work is located. §2253.076(c) caps a retainage claim at the contract figure and states a claim for retainage "is never valid for an amount greater than 10 percent of the amount of that contract".

Two provisions rescue a badly drafted bond. §2253.023(a) construes a bond furnished in an attempt to comply as complying, and §2253.023(b) requires any provision that expands or restricts a right or liability under the chapter to be disregarded. §2253.027(a)(1) goes further: an entity that fails to obtain the payment bond is "subject to the same liability that a surety would have".

The two Texas limitation periods do not start on the same day — Government Code §2253.078(a) runs from final completion, abandonment or termination of the public work contract for a performance bond claim, while §2253.078(b) runs from the date the claimant mailed its notice for a payment bond claim, and §2253.073(a) sets the earliest possible suit at the 61st day after that mailing.

Does the federal side work the same way?

Direct answer: same two bonds, different arithmetic, and one waiver rule Texas has no counterpart to in this chapter.

40 U.S.C. §3131(b) requires both bonds before any contract of more than 100,000 dollars for construction, alteration or repair of a federal public building or public work, "which become binding when the contract is awarded". The performance bond is in "an amount the officer considers adequate" at §3131(b)(1) — discretion, not a formula. The payment bond equals the total amount payable under the contract unless the awarding officer determines "in a writing supported by specific findings" that such an amount is impractical, and it "shall not be less than the amount of the performance bond" at §3131(b)(2). §3131(c)(1) requires every performance bond to cover taxes collected, deducted or withheld from wages, with the 90-day and 180-day notice limits at (c)(2) and the one-year bar at (c)(3)(B). §3131(d) lets a contracting officer waive both bonds for work to be performed in a foreign country where furnishing them is impracticable, and §3131(e) preserves the officer's authority to require other security.

Below the threshold, §3132(a) directs the Federal Acquisition Regulation to provide alternatives to payment bonds for contracts "more than $25,000 and not more than $100,000", and §3132(b) has the contracting officer select among them and name the selection in the solicitation. This page does not list those alternatives, which are set by that regulation rather than by the statute.

Enforcement differs too. §3133(b)(1) gives a 90-day wait before suit; §3133(b)(2) adds a 90-day written notice for a claimant whose contract is with a subcontractor; §3133(b)(3) sets venue and provides that suit is brought in the name of the United States for the use of the claimant "regardless of the amount in controversy"; §3133(b)(4) bars suit later than one year after the claimant's last labour or material; §3133(b)(5) exempts the Government from costs.

And §3133(c) is the provision to put in front of anyone drafting a subcontract. A waiver of the right to sue on a payment bond required under that subchapter is void unless it is in writing, signed by the person whose right is waived, and executed after that person has furnished labour or material for the performance of the contract.

A pre-signed waiver of payment bond rights does not survive on federal work — 40 U.S.C. §3133(c) makes the waiver void unless it is in writing, signed by the person whose right is waived, and executed after that person has already furnished labour or material; this page checked Government Code Chapter 2253 in full and found no counterpart section there.

What changes on private work?

Direct answer: the payment bond becomes optional, and it runs in favour of the owner.

Property Code §53.201(a) states that an original contractor with a written contract with the owner "may furnish at any time a bond for the benefit of claimants". §53.201(b) explains what the owner gets: once a valid bond is filed, a claimant may not sue the owner or the owner's property, and the owner is relieved of obligations under Subchapter D or E. §53.202 then sets six requirements, of which three are easy to miss: the penal sum must be "at least equal to the total of the original contract amount" at (1); the bond must "be in favor of the owner" at (2); and the condition at (5) covers prompt payment for labour, subcontracts, materials and specially fabricated materials, plus "normal and usual extras not exceeding 15 percent of the contract price".

That is not the same instrument as the public work payment bond, even though both are called a payment bond. §53.203(a) requires the bond and the contract to be filed with the county clerk where the property sits. §53.206(a) requires notice under §53.056 and §53.057 to perfect a claim other than by fixing a lien, and opens "Except as provided by Subsection (b)" — §53.206(b) removing the §53.057 notice to the surety for a retainage claim where the claimant has a direct contractual relationship with the original contractor — while §53.206(c) relieves a claimant who gives those notices from filing a lien affidavit. §53.208(a) sets a 60-day wait before suit, and §53.208(d) splits the limitation period — one year from perfection if the bond was recorded when the lien was filed, two years if it was not. §53.210 divides a short bond pro rata: where valid claims exceed the penal sum, "each claimant is entitled to a pro rata share of the penal sum". §53.211(a) and (b) carry the same attempted-compliance rescue as the public work chapter.

Government Code §2252.909(b) sits between the two worlds. A lease of public property must contain terms requiring the lessee to make each construction contract conditional on a payment bond conforming to Subchapter I, Chapter 53, Property Code, and a performance bond equal to the contract amount, and to give the entity a notice of commencement at least 90 days before work begins; §2252.909(e) makes material misrepresentation in that notice a Class A misdemeanour.

The private work payment bond is optional and runs the other way — Property Code §53.201(a) says the original contractor "may furnish" it, §53.202(2) requires it to "be in favor of the owner", and §53.201(b) provides that once a valid bond is filed a claimant may not sue the owner or the owner's property.

What this page does and does not tell you

It tells you which statute creates each of the three bonds, which thresholds and which verbs each uses, who the named beneficiary is, and what the notice and limitation dates are on Texas public work, federal work and Texas private work.

It does not tell you three things.

  1. Anything you could budget from. Every figure here is a statutory threshold, a statutory percentage or a day count, each tagged with the section it comes from.
  2. What a surety will ask you for. Documentation, years of statements and personal indemnity requirements are underwriting practice and do not come from these statutes. This page does not list them.
  3. Whether your own notice was timely, or your clause enforceable. Those turn on dates and documents this page cannot see, and they are legal questions; involve a lawyer alongside a licensed agent.

Common misconceptions

What people say What to check instead
"Texas requires a bid bond on public work." §2253.021(a) requires only the performance and payment bonds; the bid bond is permissive under Local Government Code §262.032(a)
"A bid bond means I promised to do the job." TDI's Bond Resources page defines default as failing to obtain the performance and/or payment bond, and limits coverage to the gap to the next qualifying bidder
"The payment bond protects the general contractor." §2253.021(c)(1) names payment bond beneficiaries; §2253.001(2) says the chapter, not the contract, decides who they are
"Both limitation periods run from completion." §2253.078(b) runs from the date the claimant mailed notice
"Design-build fees can be bonded too." §2269.311(a) and §2269.367(a) state the design portion is not required and may not be covered
"Private owners must demand a payment bond." §53.201(a) says the original contractor "may furnish" one, and §53.202(2) puts it in favour of the owner
"A waiver signed at contract execution holds." 40 U.S.C. §3133(c) voids it unless signed after labour or material was furnished
"A bond that departs from the statute is worthless." §2253.023(a)(b) and Property Code §53.211(a)(b) construe it as complying and disregard the departing provision

Every row is sourced in the sections above it; no new source is introduced here.

FAQ

Q: Can the awarding entity tell me which surety company to use? No. Government Code §2253.021(g) provides that a governmental entity may not require a contractor for any public building or other construction contract to obtain a surety bond from any specific insurance or surety company, agent or broker. §2253.021(h) separately bars a reverse auction procedure for services related to a contract for which a bond is required under that section.

Q: What has to be printed on the bond itself? Government Code §2253.021(f) requires the bond or an attachment to display clearly and prominently the surety company's name, mailing address, physical address and telephone number including area code for notices of claim, or the Texas Department of Insurance toll-free number under Subchapter B, Chapter 521, Insurance Code, with a statement that the address can be obtained by calling it. Property Code §53.202(6) carries the same structure for the private work bond.

Q: How do I get a copy of a bond I am not a party to? Government Code §2253.024(a)(2) requires the prime contractor to provide copies on written request, within the period set by §2253.024(c) — not later than the 10th day after receipt. §2253.026(a) and (d) require the governmental entity to furnish a certified copy of the payment bond and the contract to an applicant who submits the affidavit described there. On federal work the equivalent is 40 U.S.C. §3133(a).

Q: Who is allowed to execute these bonds in Texas? Insurance Code §3503.005(a) provides that a bond made, given, tendered or filed under Chapter 53, Property Code, or Chapter 2253, Government Code, "may be executed only by a surety company that is authorized to write surety bonds in this state", with further requirements above a bond amount of 100,000 dollars.

Related pages

Next step

Bring the solicitation or contract pages that mention bid security, performance and payment bonds, the contract amount, and the name of the awarding entity, and book a review through the contact page. We will sort the requirements into what the statute compels, what the entity merely may ask for, and what only defers a deadline. Licensee: Deqing Yang, Texas individual agent license 1515542; the agency SLOOD, L.L.C. holds Texas General Lines Agency license 1557787, and licensing details are on the team and licensing page. Coverage placed by SLOOD, L.L.C., doing business as Allwin Insurance Agency. What is covered and what is paid is decided by the insurer under the policy.

Sources and update log

No. Source and locator What this page uses it for
1 Texas Government Code Chapter 2253 §2253.001(2); §2253.021(a)(b)(c)(d)(e)(f)(g)(h); §2253.023(a)(b); §2253.024(a)(2), (c); §2253.026(a)(d); §2253.027(a)(1); §2253.041(b)(c)(d); §2253.046(a); §2253.047(c)(d)(e); §2253.073(a); §2253.076(c); §2253.077; §2253.078(a)(b). This page read the whole chapter
2 Texas Government Code Chapter 2269 §2269.258(a)(b); §2269.311(a)(b)(c); §2269.367(a)(b)(c). This page read selected sections, not the whole chapter, together with an inventory of the chapter's 88 section headings
3 Texas Local Government Code §262.032 and Chapter 271 §262.032(a)(d); §271.021(2); §271.024; §271.059. This page read selected sections of each, not the whole chapters
4 Texas Property Code Chapter 53 §53.201(a)(b); §53.202(1)(2)(5)(6); §53.203(a); §53.206(a)(b)(c); §53.208(a)(d); §53.210; §53.211(a)(b). This page read Subchapter I plus two further sections, not the whole chapter
5 Texas Government Code §2252.909 §2252.909(b)(e). This page read two passages of that chapter, not the whole chapter
6 40 U.S.C. §3131, §3132, §3133 §3131(b)(1)(2), (c)(1)(2)(3), (d), (e); §3132(a)(b); §3133(a), (b)(1)(2)(3)(4)(5), (c). All four sections §§3131–3134 were retrieved in full
7 Texas Insurance Code §3503.005 §3503.005(a). This page read the whole chapter
8 Texas Department of Insurance: Bond Resources The bid and proposal bond default definition and coverage limit, and the statement that the successful bidder is expected to furnish the necessary performance and/or payment bond to start work. Page self-dated 2/25/2026

Author / reviewer: Deqing Yang, Texas General Lines Agent #1515542 ; coverage placed by SLOOD, L.L.C., doing business as Allwin Insurance Agency | Applies to: Texas / 2027